Legacy Capital Project Work Scheduled For Summer 2025

As part of the Legacy Capital Project, approved by residents in 2020, improvements and renovations will be made to all eight school buildings and the transportation facility over the next several years.  The project will create energy and operational efficiencies throughout the District as well as protect the community’s long-term investment in our school facilities.

Learn more about the work happening in our school buildings:

Caroline Street Elementary School

Caroline Street will be closed for the summer.  The main office will be temporarily relocated to Geyser Road Elementary.

  • Select Classroom renovations
  • Secure Vestibule Renovations
  • Select window and door replacements
  • Kitchen renovations, including a new serving line
  • Stage Lighting replacement
  • Mechanical, electrical, and plumbing upgrades
  • Select roofing replacement
  • Traffic improvements to drop-off & bus loop area

    Division Street Elementary School

    • Stage folding partition replacement

    Geyser Road Elementary School

    • New main entrance and secure vestibule
    • Stage lighting replacement

    Lake Avenue Elementary School

    Lake Avenue will be closed for the summer. The main office will be temporarily relocated to Dorothy Nolan Elementary.

    • Classroom renovations on the third floor
    • Select bathroom renovations
    • Select window and door replacements
    • Kitchen renovations, including a new serving line
    • Cafeteria Floor Replacement
    • Electrical system upgrades
    • Select roofing replacement
    • Asphalt replacement by outdoor play area

    Maple Avenue Middle School

    • Tennis court replacement
    • Softball dugout replacement
    • Emergency generator replacement