As part of the Legacy Capital Project, approved by voters in 2020, improvements and renovations will continue at all eight school buildings and the transportation facility over the next several years. The project is designed to enhance learning environments, improve energy and operational efficiencies across the district, and protect the community’s long-term investment in our school facilities.
Learn more about the work happening in our school buildings:
Lake Avenue Elementary School
Lake Avenue will remain open during construction.
- Auditorium stage lighting and rigging replacement
- First-floor bathroom renovation near the auditorium
- Replacement of select stairwell doors
- Paving and site improvements along Marion Place
Construction Impact: Marion Place will operate as a one-way street during construction. There will be no parking on the west side of Marion Place between the playground and Lake Avenue.
Geyser Road Elementary School
Geyser Road Elementary School will be closed for the summer. The main office will be temporarily relocated to Caroline Street Elementary School. The playground will remain open throughout the summer.
- Select classroom renovations
- Library renovation, including a new corridor that will allow passage through the center of the building without going through the library
- Select bathroom renovations
- Select roofing replacement
- Kitchen renovations
- Mechanical and electrical upgrades
Saratoga Springs High School
Saratoga Springs High School will remain open during construction.
- Select classroom renovations on the second floor of D-Wing
- Select bathroom renovations
- Music Room E108 renovation, including a new sound booth
- Library renovations
- Construction of a Learning Stair and Learning Commons in A-Wing
- Secure vestibule at the main entrance
- Boys’ locker room renovations in the White Gym
- Cafeteria skylight replacement
- Construction of a satellite cafeteria
- Mechanical and electrical upgrades
Construction Impacts:
- The library will temporarily relocate to the Spa Room for the 2026–2027 school year and return to its original location in August 2027.
- The main entrance will be closed during the summer. Visitors should use the entrance to the left of the main entrance to access A-Wing.
- The bus loop from the student parking lot to the A-Wing entrance will be closed during construction.
- The boys’ locker room will be closed from September through December 2026.
Transportation Facility
- Boiler replacements
- Fuel tank replacements